Crawling fast track (With Photos)

Photos: Pratik Ghimire

Crawling fast track (With Photos)

I have closely followed the Kathmandu-Tarai Fast Track national pride project for over two years. Whenever I’ve inquired about the project with the Nepali Army, which is responsible for its execution, they assert that everything is on track. However, the actual on-site progress tells a different story.

nullnull

Since the government entrusted the project to the army six years ago, the deadline has been extended four times. The most recent deadline is set for April 2027. But the progress of the fast track stands at a mere 28.56 percent, with financial progress at 29.44 percent.

nullnull

During my recent visit to the site, my primary focus was on the tunnels. I visited the construction site of three tunnels—Mahadevtar, Dhedre, and Lendanda. Work on three other tunnels has yet to start.

nullnull

Currently, out of the total 6.415 km length of three tunnels, 3.592 km has been completed, marking a progress rate of 56 percent. This might be a hopeful sign.