Crawling fast track (With Photos)
Photos: Pratik Ghimire
![Crawling fast track (With Photos)](https://annapurnaexpress.prixacdn.net/media/albums/fast_track_bridge_K1hg2u3jKz.jpg)
I have closely followed the Kathmandu-Tarai Fast Track national pride project for over two years. Whenever I’ve inquired about the project with the Nepali Army, which is responsible for its execution, they assert that everything is on track. However, the actual on-site progress tells a different story.
Since the government entrusted the project to the army six years ago, the deadline has been extended four times. The most recent deadline is set for April 2027. But the progress of the fast track stands at a mere 28.56 percent, with financial progress at 29.44 percent.
During my recent visit to the site, my primary focus was on the tunnels. I visited the construction site of three tunnels—Mahadevtar, Dhedre, and Lendanda. Work on three other tunnels has yet to start.
Currently, out of the total 6.415 km length of three tunnels, 3.592 km has been completed, marking a progress rate of 56 percent. This might be a hopeful sign.
related news
Editorial: Air safety woes
July 26, 2024, 10:52 a.m.
Climate change, road, and hydropower construction hit Annapurna Region hard
July 26, 2024, 10:46 a.m.
The week that was
July 26, 2024, 9:48 a.m.
Monsoon, dengue and weakness in public health infrastructure
July 25, 2024, 11:38 a.m.
18 dead in Kathmandu plane crash
July 25, 2024, 10:34 a.m.
Kathmandu plane crash: It will take three days to conduct postmortem: TUTH
July 25, 2024, 9:27 a.m.
BRI in focus as foreign minister begins work
July 25, 2024, 12:08 a.m.
Government forms five-member commission to investigate Saurya Airlines plane crash
July 24, 2024, 7:16 p.m.
Comments