Three years on; Jajarkot earthquake victims still living in makeshift shelters

It has been three years since Bagmati Singh of Bheri Municipality-2, Jajarkot, began living in a makeshift tin shelter after the earthquake destroyed her house on November 3, 2023. 

Her family of five initially lived under a tarpaulin before moving into the temporary shelter, hoping to rebuild their home soon.

Ganesh Tiruwa, also from Bheri Municipality-2, has faced an even worse situation. After his house was destroyed in the earthquake, his family of six moved into a temporary shelter. But a landslide on August 15 this year swept away the shelter as well, leaving them without a home.

Although the government decided to provide Rs 400,000 per household for permanent housing, procedural delays in releasing the funds have left earthquake victims struggling to rebuild their homes.

However, the family is still waiting for the government grant promised for reconstruction. Successive governments assured earthquake victims that their homes would be rebuilt, but little progress has been made.

Candidates from various political parties also promised during election campaigns to prioritise reconstruction. 

Despite a new government taking office, Singh’s house remains unreconstructed. 

Unable to afford reconstruction herself, she said her family had spent three years waiting for government assistance.

"Who will listen to the problems of poor families like ours?" she asked.

Strong winds have blown away many temporary tin shelters. During winter, rainwater and dew seep through their roofs, while the tin sheets become unbearably hot in summer. Tiruwa said delays in reconstruction had compounded the suffering of families already struggling to survive.

The government completed the first phase of the Detailed Damage Assessment(DDA) nearly a year ago, but not a single permanent house has been reconstructed so far.

The assessment classified damaged houses into three categories  requiring reconstruction, retrofitting and minor repairs. However, many earthquake-affected households have complained that they were left off the list of eligible beneficiaries. Dissatisfaction with the DDA findings, complicated administrative procedures and delays in agreements and verification have further slowed the reconstruction process.

Bheri Municipality Mayor Chandraprakash Gharti said the process had been delayed partly because of a shortage of technical personnel required to verify eligible beneficiaries.

He said the municipality had decided last March to conduct a reassessment of households excluded from the initial DDA and had forwarded the decision to the relevant authorities. However, the reassessment process has yet to begin.

"Despite completing all the procedures required at the local level and forwarding the documents, the federal government has been unnecessarily delaying the process," Gharti said.

Victims have also blamed delays and indifference on the part of local administrations, municipalities and the National Disaster Risk Reduction and Management Authority (NDRRMA) for leaving reconstruction in limbo.

The magnitude 6.4 earthquake that struck shortly before midnight on November 3, 2023, caused extensive loss of life and property in Jajarkot and neighbouring Rukum West.

According to NDRRMA data, 154 people were killed, 101 in Jajarkot and 53 in Rukum West. A total of 26,557 houses were completely destroyed and 35,455 partially damaged. Another 364 people were injured.

In Jajarkot alone, 48,516 households were identified as eligible for temporary housing assistance. Of these, 35,583 families received Rs 50,000 each, according to the District Administration Office.

The DDA report released by the authority identified 14,245 houses in Jajarkot for reconstruction and 12,744 for retrofitting. Households approved for reconstruction are entitled to Rs 400,000 each, while those eligible for retrofitting can receive up to Rs 300,000.

The District Administration Office said 1,344 households in Jajarkot had so far completed the required procedures and been approved as beneficiaries.

Chief District Officer Navaraj Baral said the first instalment of Rs 50,000 each had been released to 188 households for reconstruction, nearly a year after agreements were signed.

"Reconstruction will now gain momentum," he said.

More than 50 technical personnel and engineers are expected to arrive at the Jajarkot office of the reconstruction authority immediately after Tihar. The process of reassessing households excluded from the DDA will also move forward after the festival, Baral said.

He added that the reconstruction guidelines, which had created obstacles in the process, were expected to be amended soon.

"Once the guidelines are revised, some of the difficulties in reconstruction will be resolved and the work will gather pace," he said.

The government had initially assured earthquake victims that permanent housing would be provided within six months. Three years later, many families are still waiting.