The Bhotekoshi-Trishuli flood that surged through Rasuwa, Nuwakot, and Dhading has left approximately 1,451 dead and 5,745 missing as per the National Disaster Risk Reduction and Management Authority (NDRRMA). Damage and losses are estimated at over Rs 408bn, and reconstruction will require around Rs 723bn. The effect on infrastructure has been severe: 13 hydropower projects and five solar plants were hit, nearly 70 kilometers of road were damaged, 33 motorable bridges were washed away, and 68 suspension bridges were damaged.
Since the disaster, there has been widespread talk of making climate risk assessment mandatory for infrastructure projects. This is welcome news and exactly the right direction. Yet similar procedures, such as the Initial Environmental Examination (IEE), and the Environmental Impact Assessment (EIA) have long been used to screen projects before approval. However, often communities, scholars, and activists have repeatedly questioned how well they were assessed and suggestions implemented.
EIA was meant to protect people, rivers, and investments from poorly planned projects, yet it was long treated as a hurdle to clear red tape rather than a genuine examination of risk. The World Commission on Dams made the same observation as early as 2000, noting that assessments were often carried out too late and too narrowly to shape decisions. So, before we celebrate climate risk assessment as the fix, we need to ask an uncomfortable question: what, exactly, will stop it from becoming another formality?
A good idea that travelled well
EIA began with the US National Environmental Policy Act of 1969, which for the first time required that the environmental consequences of highways, dams, and power plants be studied before approval. The idea spread quickly. The 1987 Brundtland Report placed it within the wider agenda of sustainable development, and the 1992 Rio Earth Summit made it a global norm. Principle 17 of the Rio Declaration called on states to assess activities likely to cause significant environmental harm, and Principle 19 required them to notify neighbouring states of projects with transboundary effects. Within a few decades, more than a hundred countries had adopted EIA systems.
Nepal was an early adopter, at least in spirit. Its national plans of the 1980s called for assessing major infrastructure, and the National EIA Guidelines of 1993 gave the process practical shape. The Environment Protection Act of 1996 and the Environment Protection Rules of 1997 made IEE and EIA legally mandatory for prescribed projects, required public hearings, and assigned monitoring responsibilities to line ministries. The Environment Protection Act 2076 BS (2019) and its 2020 Rules replaced this framework, adding provisions on pollution control and climate change. Alongside national law, the World Bank and the Asian Development Bank have applied their own safeguard policies to the projects they finance, updating them regularly.
On paper, Nepal has had a mature assessment system for nearly three decades.
How EIA became a formality
The problem is what happens between the rules and reality. In Environmental Assessment: Untold Realities, Batu Uprety, former Joint Secretary and Chief of the Climate Change Management Division at the then Ministry of Environment, and former Team Leader of Nepal's National Adaptation Plan formulation process, documents that many EIA reports have been copied and pasted from reports prepared for other projects. Yet these reports shape the future of entire regions, their residents, and the people who will depend on the infrastructure. Projects built on false information cannot deliver sustainable or ethical outcomes.
One could argue that at its core, the process is weak because institutions are. Developers hire and pay the consultants who assess their own projects. Reports are rarely made public in a form, or a language, that affected communities can read. Public hearings do take place for major infrastructure projects, but questions remain about who is consulted and whose voices are heard. Many affected people do not even know when or where the hearings were held, so consultations often happen for namesake only.
Those who questioned the process have often been pushed to the margins. Activists who challenged the EIA process and advocated for affected communities were labelled anti-development. Scholars who weighed the environmental, biodiversity, and economic costs of projects against their benefits were often given the same label. From mid-2000, this narrative had become so powerful that many of these voices have fallen silent. Communities affected by infrastructure projects across the country have raised concerns that were not often heard.
What climate risk assessment must do differently
In the aftermath of the Bhotekoshi-Trishuli flood, climate risk and multi-hazard assessments are being proposed as the way to prevent or reduce future losses. They are the right tools. But if they are introduced into the same system, they will meet the same fate. Five changes would make the difference.
First, independent assessments should be conducted by a body that is not paid by, and does not answer to, the project developer. As long as the proponent pays the assessor, the conflict of interest remains. Strict monitoring and penalties for violation of assessment procedures are essential. Consultants who submit copied or falsified assessments should lose their accreditation, and developers who ignore assessment findings should face penalties strong enough to matter. Monitoring, by a team that includes government officials, local communities, and multi-disciplinary experts, must continue through construction and operation.
Second, the Bhotekoshi-Trishuli flood showed that danger can originate across the border, which makes transboundary data sharing with China on glacial lakes and upstream hazards essential. These data-sharing mechanisms should be strengthened, with Nepali experts involved so that they can monitor the data regularly themselves.
Third, project-specific assessments must be accompanied by cumulative risk assessment. A single glacial lake or unstable slope can threaten several projects along the same river, so assessment must look at the whole basin, not one project at a time.
Fourth, climate risk assessment should adopt a nexus approach rather than assessing infrastructure in isolation. Hydropower, irrigation, agriculture, drinking water, ecosystems, roads, and settlements are interconnected, particularly within a river basin. Damage to one system can quickly affect others. Climate risk assessment should therefore examine these interdependencies and potential trade-offs and consider how decisions in one sector may create risks or reduce resilience in another.
Fifth, affected communities must be at the center of these assessments, involved early enough to influence decisions. The assessments should be publicly disclosed, with summaries in Nepali and local languages, before approval rather than after. When local people, researchers, or activists raise issues in an assessment, those concerns should be investigated, not dismissed as anti-development.
Multilateral lenders have begun incorporating climate risk into their safeguards, most explicitly in ADB’s new climate standard, which has been in force only since January 2026. Nepal should develop its own assessment standards and keep updating them. Climate risk assessment could save lives and protect billions of rupees in public investment. But a new tool placed in an old system will produce old results. If Nepal wants this reform to be more than paperwork, it must also fix the system that turned EIA into a formality.
The author works with the International Water Management Institute (IWMI). She dedicates this article to those affected by the Bhotekoshi flood and to those who advocate and work for involuntarily displaced people