The bill for rebuilding

One month after an ice-and-rock avalanche in the upper Lhende Khola watershed triggered a massive debris flow and flooding along the Bhotekoshi–Trishuli–Narayani river system, Nepal is moving from an immediate rescue response towards one of the country’s largest post-disaster recovery and reconstruction exercises. 

The avalanche occurred about 20 kilometers upstream of the Rasuwagadhi border point, sending debris and floodwaters downstream and causing extensive damage to infrastructure, homes, livelihoods and essential services.

The government has continued search and rescue operations while beginning preparations for short-, medium- and long-term recovery and reconstruction. It is also seeking financial support from India, China and other international partners to meet the enormous cost of rebuilding. A Rapid Damage and Needs Assessment (RDNA) has put the total economic impact of the disaster at $2.7bn, comprising $1.81bn in physical damage and $883.32m in economic losses.

But the bill for rebuilding is considerably higher. The assessment estimates that Nepal will require $4.77bn, or Rs 723.32bn, for recovery and reconstruction. Of this, $57.66m is required during the first six months, while $4.72bn is projected for recovery and reconstruction beyond the first six months.

The difference between the damage bill and the recovery requirement reflects the fact that reconstruction is not simply about replacing what was destroyed. The recovery program also incorporates disaster-risk reduction, stronger and more resilient infrastructure, debris management and measures intended to make affected communities less vulnerable to future disasters.

Infrastructure has emerged as the largest component of the recovery challenge. It accounts for 46.55 percent of the assessed disaster effects, while the productive sector accounts for 36.83 percent and the social sector 16.62 percent. The composition changes significantly when the focus shifts from damage and losses to reconstruction needs. Infrastructure accounts for 65.47 percent of total recovery needs, followed by social sectors at 14.32 percent, cross-cutting requirements at 13.19 percent and productive sectors at 7.02 percent.

The energy sector represents the largest single reconstruction requirement. Hydropower and electricity-grid infrastructure suffered $889.21m in physical damage, equivalent to 49.07 percent of total assessed physical damage. Economic losses in the energy sector are estimated at another $107.91m. Yet rebuilding the energy system will cost substantially more.

The assessment estimates $2.58bn in energy-sector recovery needs. Road reconstruction requires another $364.28m, while $119.9m is estimated for bridges. Further requirements have been identified for telecommunications, water supply and sanitation, irrigation and river-training infrastructure, and household renewable energy. The restoration of these networks will have consequences beyond repairing physical structures.

Roads and bridges determine access to affected settlements, markets and reconstruction sites, while electricity, telecommunications and water systems are essential to restoring normal economic and social activity.The social sector has also sustained substantial damage.

Private buildings account for $421.74m, or 94.15 percent of total social-sector damage. Recovery needs for private buildings alone are estimated at $632.61m. The remainder of the social-sector requirement covers public buildings and facilities, education, health and cultural heritage.

Although these sectors represent a smaller share of the overall financial requirement, the RDNA notes that their financial size should not be interpreted as an indication of their importance. Restoring schools, health facilities and other essential public services will be critical to the recovery of affected communities.

The disaster has also disrupted economic activity and livelihoods across the affected areas.

The productive sector recorded $200.05m in physical damage and $765.07m in economic losses. Economic activities and livelihoods alone account for 86.61 percent of all assessed economic losses.

The estimated recovery requirement for this subsector is $300.08m. Agriculture, fisheries, livestock and banking make up the remaining productive-sector requirements.

The assessment cautions that recovery needs should not be interpreted as compensation for accumulated economic losses. The two figures measure different things: economic losses capture the disruption to income and activity, while recovery needs to estimate the interventions required to restore and rebuild productive capacity. 

Perhaps the clearest indication that the government is looking beyond immediate reconstruction is the size of the cross-cutting recovery requirement. Cross-cutting recovery needs are estimated at $629.91m, of which $625.52m is allocated to disaster-risk reduction. The remainder covers debris management and inclusive recovery measures.

This means a significant portion of the reconstruction programme will be aimed not merely at restoring what existed before the flood, but at reducing the risk of similar disasters in the future.

Energy, private buildings and disaster-risk reduction alone account for $3.84bn—or 80.35 percent—of the total recovery requirement.

The concentration of resources in these three areas means that detailed engineering assessments, site investigations and activity-level costing will be particularly important as the government moves from the RDNA towards an implementable recovery programme. The immediate recovery requirement is comparatively small when measured against the overall reconstruction bill.

The RDNA estimates $57.66m for the first six months, only 1.21 percent of the total recovery requirement. The remaining $4.72bn is assigned to the period beyond six months. Of the early recovery requirement, 77.20 percent is allocated to infrastructure, with roads and bridges alone accounting for 54.26 percent. The emphasis reflects the urgent need to restore physical access to affected areas. But the adequacy of the allocation for other immediate needs will depend on the

A month after the disaster, the central challenge is therefore changing.

The immediate response centred on finding missing people, rescuing those stranded by the flood and dealing with debris and damaged infrastructure. The next phase will require the government to coordinate a reconstruction program worth more than Rs 723bn while maintaining essential services and livelihoods in affected areas.

The scale of the requirement also means that domestic resources alone are unlikely to be sufficient. The government's efforts to mobilize financial and technical assistance from neighboring countries and international development partners will be an important part of the next phase. 

But the RDNA also makes clear that securing money is only one part of the task. Detailed engineering, site assessments, prioritisation, financing arrangements and implementation plans will determine how quickly the estimated recovery programme can be translated into reconstruction on the ground.

One month after the Bhotekoshi disaster, Nepal is consequently facing a recovery challenge that extends far beyond repairing flood-damaged roads, bridges and houses. It is a question of rebuilding critical infrastructure, restoring livelihoods and essential services, and deciding how much of the reconstruction should be designed to withstand the next extreme event. 

The Rs 723.31bn recovery requirement provides the scale of the challenge. The next phase will determine how that figure is converted into projects, financing and, ultimately, recovery for the communities affected by the Bhotekoshi–Trishuli–Narayani disaster.